IS 1200 – Part 6: Formwork (Centering & Shuttering)

1) Scope

Contact formwork for PCC/RCC: slabs, beams, columns, walls, footings, curved surfaces.

2) Units

  • of contact surface with concrete.

3) Main Rules

  • Classify by orientation (horizontal/vertical/soffit/curved) and finish (ordinary/fair/controlled).
  • Measure net contact area; no deduction for small openings ≤0.4 m².
  • Repetition/striking not a measurement parameter unless specified.

4) Deductions

  • Openings >0.4 m² → deduct.

5) Special Notes

  • Beam sides, beam soffit, slab soffit, column sides, wall faces all separate.
  • Chamfers/fillets usually included with formwork (state if payable).
  • Scaffolding not included unless contract says so.

6) Example

Beam 6.0×0.3×0.5 m:

  • Sides area = 2 × (6.0 × 0.5) = 6.0 m²
  • Soffit (bottom) area = 6.0 × 0.3 = 1.8 m²
    Total = 7.8 m² (measured separately as sides & soffit).

📘 IS 1200 – Part 7: Flooring, Dado, Skirting (Stone/Tiles/Terrazzo)

1) Scope

Floor, wall dados, skirting, steps/treads, thresholds in stone/tiles/terrazzo.

2) Units

  • (area work)
  • m (skirting/beading if linear)
  • No. (steps/treads if specified)

3) Main Rules

  • Classify by material, thickness, finish (polished/honed/antiskid), location.
  • Include bedding mortar where specified as part of item, or keep separate if the spec says so.
  • Joints/grouting included unless specified.

4) Deductions

  • Openings/shafts >0.1 m² → deduct.
  • Small cutouts for pipes/holdfasts ignored.

5) Special Notes

  • Skirting/dado: height stated; corners, mouldings extra.
  • Grooves/nosings measured separately if specified.

6) Example Granite flooring 18 mm over 20 mm CM bed: area 85.00 m², floor trap 0.20×0.20 (0.04 m²) × 6 nos = 0.24 m² ignored. Pay = 85.00 m².