Part No. | Scope | Unit of Measurement | Classification | Special Notes |
1 | Earthwork (excavation, filling, banking, etc.) | m³, m², m, tonne | Type (excavation/filling), Soil/Rock, Lead/Lift, Dewatering | Timbering/shoring included; Deduction for pits >0.5 m² |
2 | Concrete Work (plain/reinforced) | m³, m² | Mix type, Thickness, Reinforcement inclusion | Centring/shuttering included unless specified |
3 | Brickwork | m³ | Brick class, Mortar mix, Bond, Orientation | No deduction ≤0.1 m² openings; Arches measured separately |
4 | Stone Masonry | m³ | Type (rubble, ashlar), Mortar, Finish | No deduction ≤0.05 m² holes |
5 | Reinforced Concrete | m³ (concrete), kg/tonne (steel) | By grade, member type | Formwork separate; laps, hooks included |
6 | Formwork | m² | Type (slab, beam, wall, column) | Re-use not considered; Measured on contact surface |
7 | Damp-Proof Course (DPC) | m², m | Thickness, Material type | Plinth protection excluded |
8 | Steelwork (Structural) | tonne, kg | Type (rolled, built-up, truss) | Bolts/rivets/welding included |
9 | Roof Covering & Cladding | m², m | Material (tiles, AC, GI sheets), Slope | Laps included; Deduction >0.4 m² openings |
10 | Ceilings (false ceilings, soffits) | m², m | Material (gypsum, AC, wood), Type | Frames measured separately |
11 | Flooring, Paving, Dado, Skirting | m², m³, m | Material (stone, tile, wood, PVC) | Borders, inlays measured separately |
12 | Plastering & Pointing | m², m | Thickness, Coats, Pointing type | Deductions >0.5 m² openings |
13 | Whitewashing, Colour washing | m² | No. of coats | Ceiling/walls measured separately |
14 | Painting, Polishing, Varnishing | m², m | Material, Surface type | Door/window shutters measured on one side only |
15 | Glazing | m² | Glass type, Thickness | Openings <0.1 m² not deducted |
16 | Woodwork & Joinery | m³, m², m | Type (frames, shutters, partitions) | Fixtures included unless specified |
17 | Roadwork (earthwork, soling, macadam, etc.) | m³, m², m³/100 m² | Type (earthwork, WBM, asphalt, concrete) | Compaction included |
18 | Demolition & Dismantling | m³, m², m | By type (brick, concrete, steel, timber) | Salvaged material excluded |
19 | Water Supply, Plumbing, Sanitary Installations | m, each | Pipe material, Diameter, Fixture type | Excavation/backfilling measured separately |
20 | Well Foundations | m, m³ | Diameter, Type (open/caisson) | Sinking, plugging included |
21 | Pile Work | m, m³, tonne | Type (driven, bored, precast) | Reinforcement included; Test piles separate |
22 | Steel Reinforcement & Fabrication | tonne, kg | Bars by dia. & shape | Laps, hooks included; Chairs separate |
23 | Pile Driving | m, each | Type (timber, precast, steel) | Test load measurement separate |
24 | Ferrules, Sealing, Conduits | each, m | Size, Type | Fixing charges included |
25 | Lining of Canals/Water Courses | m², m³ | Type (brick, stone, concrete) | Joints measured separately |
26 | River Training & Protection Works | m³, m² | Type (revetment, pitching, gabion, apron) | Boulder size classification |
27 | Earthwork in Rough Excavation | m³ | Type (borrow, cutting, embankment) | Lead/lift measured |
28 | Hydraulic Structures (Dams, Barrages) | m³, m² | Concrete, Masonry, Formwork | Grouting separate |
29 | Prestressed Concrete | m³, tonne, m | Pre-tensioned, Post-tensioned | Jacking, ducts, sheathing measured separately |
30 | Pumping Installations | each, set | Type, Capacity | Electrical accessories separate |
31 | Anti-Termite Treatment | m², m³ | Stage (pre/post construction) | Chemicals & application included |
32 | Aluminium Work | m², kg | Type (partition, window, door) | Glazing measured separately |
33 | Water Proofing Work | m² | Method (membrane, integral, coating) | Joints measured separately |
34 | Fencing & Gates | m, m², each | Type (barbed wire, chain link, RCC posts) | Posts measured separately |
35 | Road Furniture & Misc. Works | each, m² | Type (sign boards, guard rails, markers) | Foundations separate |