Class C – Geotechnical and Other Specialist Processes (CESMM4)

This class covers all specialist geotechnical works that improve ground strength, stability, permeability, or prepare the foundation ground before and during construction.

While Class B (Ground Investigation) is about understanding soil conditions, Class C is about improving or altering soil and rock conditions to make them suitable for construction.


1. Purpose of Class C

  • To include specialist ground treatment and support methods.
  • To ensure proper measurement rules for complex geotechnical works.
  • To separate these works from normal excavation, piling, and earthworks (covered in other CESMM classes).

2. Main Subdivisions of Class C (as per CESMM4)

C1. Ground Treatment (Stabilisation/Improvement)

  • Grouting (cement, chemical, polyurethane).
    • Pressure grouting, compaction grouting, jet grouting.
  • Soil Stabilisation by lime, cement, fly ash.
  • Vibro-compaction / Vibro-replacement (Stone Columns).
  • Dynamic compaction (dropping heavy weights).
  • Permeation grouting to reduce permeability.
  • Measurement Unit: m³ of treated soil, or Linear metre (m) of grout holes/columns.

C2. Groundwater Control (Specialist Dewatering)

  • Wellpoint systems.
  • Deep wells with pumps.
  • Cut-off walls (slurry walls, diaphragm walls, sheet piles for groundwater exclusion).
  • Recharge wells to control drawdown.
  • Measurement Unit: m of well installed, or per system Lump Sum (LS).

C3. Ground Reinforcement (Anchors, Nails, Micropiles)

  • Soil nailing (steel bars drilled & grouted into soil).
  • Ground anchors (prestressed or passive).
  • Micropiles (small-diameter piles, <300 mm).
  • Rock bolts and dowels.
  • Measurement Unit: Linear metre (m) of installation, or Each (No.).

C4. Ground Freezing / Ground Heating

  • Artificial ground freezing for tunnelling, shaft sinking, and deep excavations.
  • Ground heating (rare, used in special projects like permafrost protection).
  • Measurement Unit: Lump Sum (LS) or per treated length.

C5. Specialist Excavation Support

  • Diaphragm walls (slurry trench, reinforced concrete).
  • Secant pile walls.
  • Contiguous bored pile walls.
  • Soil mixing walls.
  • Measurement Unit: m² of wall constructed, or m³ of soil replaced.

C6. Instrumentation and Monitoring (Specialist)

  • Instruments for monitoring soil and structure performance:
    • Inclinometers (slope/retaining wall monitoring).
    • Settlement plates.
    • Strain gauges, load cells.
    • Piezometers (hydraulic/electrical).
  • Measurement Unit: Each (No.) or Lump Sum (LS) for complete monitoring package.

3. Measurement Rules (CESMM4 Guidance for Class C)

  • Items must state the process clearly (e.g., “Jet grouting 1 m diameter columns to 15 m depth”).
  • Dimensions (diameter, depth, spacing) should be clearly specified.
  • Ancillary works (pumping, spoil disposal, casing, flushing, consumables) are deemed included unless specified separately.
  • Temporary works (like trial grouting, performance tests) must be described if required.
  • Monitoring is measured separately.

4. Example BOQ for Class C

Item No.DescriptionUnitQuantityRateAmount
C1.1Jet grouting 1.0 m dia columns, 12 m depthm300
C1.2Soil stabilisation by lime/cement, 1.5 m depth1200
C2.1Installation of wellpoint dewatering systemm150
C2.2Deep wells (300 mm dia) with submersible pumpNo.6
C3.1Soil nails, 25 mm dia bars, 10 m longm500
C3.2Rock anchors, 32 mm dia, tensioned, 20 m lengthNo.40
C4.1Ground freezing system for shaft (30 m depth)LS1
C5.1Diaphragm wall 600 mm thick, 20 m depth800
C6.1Inclinometers installed in boreholesNo.4
C6.2Settlement plates for embankment monitoringNo.10

5. Practical Example

👉 Suppose you are constructing a metro tunnel in soft ground:

  • You need diaphragm walls (C5) for retaining the station box.
  • Before tunnelling, you install jet grouting (C1) to stabilise weak soils.
  • Wellpoint dewatering (C2) controls groundwater inflow.
  • Ground anchors (C3) support temporary retaining walls.
  • In difficult zones, ground freezing (C4) is adopted.
  • During all this, instruments (C6) monitor settlement and wall deflections.

In short:

Class C (Geotechnical & Specialist Processes) in CESMM4 provides a structured way to measure ground improvement, dewatering, reinforcement, support systems, and monitoring instruments. It ensures these complex activities are itemized and priced transparently in BOQ.

Comments

No comments yet. Why don’t you start the discussion?

Leave a Reply

Your email address will not be published. Required fields are marked *