CESMM4 – Application of Work Classification

The work classification is the foundation of CESMM4. It ensures that every item of civil engineering work is described and measured consistently across projects.


1. Purpose of Work Classification

  • Provides a systematic structure for BOQs.
  • Ensures uniformity across different projects and consultants.
  • Avoids ambiguity in descriptions.
  • Helps contractors price works accurately and competitively.
  • Aids in cost control, variation analysis, and final account settlement.

2. Work Classification Structure

Work in CESMM4 is classified into Classes A to Z, each covering a broad type of work.

ClassDescriptionExamples of Work Items
AGeneral ItemsSite offices, mobilization, insurances
BGround InvestigationTrial pits, boreholes
CEarthworksExcavation, filling, compaction
DConcreteIn-situ concrete, formwork
EPipework – PipesLaying pipes, jointing
FPipework – Fittings & ValvesFlanges, bends, valves
GPipework – AncillariesChambers, supports
HStructural MetalworkReinforcement, steel structures
ITimber StructuresFormwork, timber bridges
JRoads & PavingAsphalt, kerbs, concrete paving
KRail TrackRails, sleepers, ballasting
LTunnelingLinings, shafts
MWaterways & MarineDredging, revetments, quays
NLand DrainageDrains, ditches, channels
OPilingBored piles, driven piles
PUnderpinningJacking, grouting
QDemolitions & AlterationsBreaking, removing, cutting
RBrickwork, BlockworkMasonry walls, partitions
SPaintingSurface prep, coating
TWaterproofingMembranes, coatings
UMiscellaneous WorksLandscaping, fencing
VDayworksLabour, materials, plant hours
WProvisional SumsLump sums for undefined works
XPrime Cost SumsNominated suppliers
YExtra Over ItemsAdjustments for special cases
ZContractor’s ObligationsWarranties, guarantees

3. How Work Classification is Applied in BOQ

Step 1 – Identify the Class

Determine which Class (A–Z) the work belongs to.

  • Example: Excavation for a foundation → Class C (Earthworks).

Step 2 – Identify the Group

Select the relevant Group within the class.

  • Example: Excavation in foundation trenches → Group C2 (Excavation).

Step 3 – Apply Features

Add Features that specify variations such as:

  • Depth ranges (e.g., 0–2 m, 2–4 m).
  • Soil type (rock, ordinary soil, soft clay).
  • Execution requirements (under water, dewatering included).

Step 4 – Define the Item

Write the full item description including:

  • Nature of work.
  • Dimensions / limits.
  • Location.
  • Standards.
  • Special conditions.

Final BOQ Item Example
“C2.1: Excavation in ordinary soil not exceeding 2 m depth for foundation trenches, including dewatering and disposal of surplus excavated material within 50 m lead.”


4. Principles in Application

  1. Consistency – Always follow CESMM4 hierarchy (Class → Group → Feature → Item).
  2. Sufficiency of Description – The item must have enough detail for pricing, but avoid redundancy.
  3. Avoid Duplication – Each work must be classified in one class only.
  4. Coverage Rule – Unless CESMM specifies otherwise, the contractor’s rate must cover labour, plant, materials, waste, handling, setting out, cleaning, and minor temporary works.
  5. Units of Measurement – Must follow SI system:
    • Length → m
    • Area → m²
    • Volume → m³
    • Weight → tonne/kg
    • Lump sum → LS

5. Practical Applications of Work Classification

  • Tendering → Contractors use classification to price items systematically.
  • Cost Control → Project teams can track costs by class (e.g., Earthworks, Concrete, Pipework).
  • Valuation of Variations → Variations can be classified under the same class and compared easily.
  • Final Accounts → Simplifies reconciliation of quantities and payments.
  • Benchmarking → Data from one project’s BOQ can be used to estimate future projects.

6. Example – Applying Work Classification

Let’s classify a Reinforced Concrete Foundation:

  1. Class: D (Concrete).
  2. Group: D2 (In-situ Concrete).
  3. Feature: Grade of concrete, location (below ground).
  4. Item:
    “D2.1: In-situ reinforced concrete of grade M25 in foundations, including placing, compacting, curing, but excluding formwork and reinforcement.”

Summary – Application of Work Classification in CESMM4

  • Provides a universal structure for describing and measuring civil engineering work.
  • Ensures clarity, fairness, and comparability in BOQs.
  • Divides works into Classes A–Z, further broken down into Groups, Features, and Items.
  • Applied consistently in tendering, cost control, and project management.

Comments

No comments yet. Why don’t you start the discussion?

Leave a Reply

Your email address will not be published. Required fields are marked *